VIENTIANE (Vientiane Times/ANN) – Tests were run last week on the first of four electricity generators at the Don Sahong hydropower plant on the Mekong River in Champassak province, after construction began in January 2016.

“According to the plan, the Don Sahong Power Company will test each energy generator every 10 days and of all the generators should be fully operational by the end of this year,” said an official from the Ministry of Energy and Mines.

“The investors in the US$500 million project include a Malaysian company, Mega First Corporation Berhad, with an 80 percent share, while ‎EDL-GEN hold the remaining 20 percent.” 